PROPOSED CONSTRUCTION OF 132KV POWER LINE TO LINK WITH THE MCWAP SUBSTATION 2

NOTICE OF APPLICATION FOR ENVIRONMENTAL AUTHORISATION IN TERMS OF THE NATIONAL ENVIRONMENTAL MANAGEMENT ACT 107 OF 1998, WATER USE LICENCE IN TERMS OF THE NATIONAL WATER ACT 36 OF 1998, AND HERITAGE PERMIT IN TERMS OF NATIONAL HERITAGE RESOURCES ACT NO. 25 OF 1999 FOR THE PROPOSED CONSTRUCTION OF ± 12KM 132KV POWER LINE, THABAZIMBI, LIMPOPO PROVINCE TO LINK WITH THE MCWAP SUBSTATION 2

Project Details

A Basic Assessment Process is required in terms of the Environmental Impact Assessment Regulations, 2014 (as amended) for the construction of a ± 12km 132kV power line from Thabazimbi combined to a new MCWAP Substation, Thabazimbi, Limpopo Province.

The project consists of:

  • Conducting a basic assessment process, environmental management programme and relevant specialist studies in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998) with EIA Regulations 2014 (as amended).
  • Conducting a water use licence application in terms of the National Water Act, 1998 (Act No. 36 of 1998) in terms of Section 21.
  • Application for a Notice of Intent to Development in terms of the National Heritage Resource Act 1999 (Act No. 25 of 1999) and sections 36 and 38.

Project Description

The following will be undertaken:

    • Construction of 100X100 m (1 Hectare) of 2x20MVA 132kV MCWAP new substation (Study Buffer zone of 2 Hectare).
    • Installation of 2x20MVA 132/11kV fully equipped transformer bays, 132kV busbar and 2x132kV line bays (one equipped initially with the other for future use).
    • Building a control room adequate to cater for all secondary plant equipment.
    • Construction of a 12km of 132kV Kingbird Power line9 (Study Corridor for 1km of which will be 500m from the centre of the power line both site).
    • Building an Access Road of 6m width and 200m length.

Registration

Be an integral part of the Environmental Impact Assessment Process. Public involvement is an essential part of any environmental assessment process. Parties wishing to register as I&APs, who wish to participate by contributing comments, or require additional information, should register and/or submit their contact details and correspondence in writing to NCC, using the below comment sheets.

All comments received will be captured, considered, and incorporated into the relevant impact assessment reports.

Registered I&APs will be notified of all comment periods and the availability of information within the process.

If you would like to register as an interested and affected party, please complete the form and return it by 10 January 2022:

Ronaldo Retief
NCC Environmental Services (Pty) Ltd
26 Bell Close, Westlake Business Park, Westlake, Cape Town
Tel: 021 702 2884
Fax: 086 555 0693
Email: ppp@ncc-group.co.za
Website: https://ncc-group.co.za/public-participation-overview

Role Players

  • ENVIRONMENTAL PRACTITIONER (EAP): NCC Environmental Services (Pty) Ltd (NCC)
  • APPLICANT: Eskom SOC Ltd, Polokwane

Commenting Period: 19 November to 10 January 2022